Guilin Shenke Technology Project
A multi-floor intelligent logistics project for Shenke Technology’s Phase 2 facility in Guilin,
featuring a combination of QR-code and visual-texture AGV navigation across three floors.
Facility Structure (3 Floors)
- Floor 1 — Warehouse Zone: Raw material warehouse, packaging material warehouse,
direct-shipping warehouse; uses Hikvision IMWS + Q3 products for smart warehousing
- Floors 2 & 3 — Shenke Production Lines: Each workshop has ~14 production lines;
visual-texture Q3 products handle smart logistics delivery
- Total AGVs: 72 latent-type units — 30 QR-navigation on Floor 1, 42 visual-texture AGVs
on Floors 2–3, plus 6 single-box CTUs per SMT workshop (Phase 1)
Equipment Deployed
Visual-Texture / QR Navigation (Floor 1): MR-Q3-600CE-C5M × 30 units
Visual-Texture AGV (Floors 2–3): MR-Q3-600VE-C5M × 42 units
QR Navigation (CTU): MR-F0-50SC-A1(H) × 12 units